Procedure of how to set or modify string capacity confirguration on Fusion Solar Web Portal
1. Access following links for Fusion Solar Web portal access:
Europe https://eu5.fusionsolar.huawei.com
Australia https://sg5.fusionsolar.huawei.com
Latin America https://la5.fusionsolar.huawei.com
2. Log in with your Installer account:

3. On the system homepage, click Settings to go to the System Setting interface

4. From “System Settings” choose “Plant Management”
From Plant Management list select the PV Plant involved and click on “Modify”

Select String configuration, select involved inverter and click on String Capacity Configuration


5. Configure string details from I-V curve (Intelligent O&M) tool:
String configuration can also modified from Parameter Configuration on the IV Curve page. In this step the configuration of the strings requests many other details.


Select the inverter and choose Configuration and the String Detailed page is displayed by default:

Select PV1 and set all the panels details. Repeat the operation for PV2 and save: