Power ON-OFF the SUN2000 inverters

888 0 0 0 0

Checking Before Power-On:


-The inverter is installed correctly and securely.

-Check that the DC switches and downstream AC output switch are OFF.

-Ground cables are connected securely, without open circuits or short circuits.

-AC output power cables are connected correctly and securely, without open circuits or short circuits.

-DC input power cables are connected correctly and securely, without open circuits or short circuits.

-The communications cables are connected correctly and securely.

-All the used connectors at the chassis bottom are sealed.

-The AC terminal cover is reinstalled.

-The maintenance compartment door is closed and the door screws are tightened.

-Idle DC input terminals are sealed.

-The idle USB port is plugged with a waterproof plug.

-Idle AC OUTPUT and COM connectors are plugged and the locking caps are tightened.


Powering On the SUN2000:


Before turning on the AC switch between the inverter and the power grid, use a multimeter to check that the AC voltage is within the specified range.

Procedure

Step 1 Turn on the AC switch between the inverter and the power grid.

Step 2 Turn on the DC switches at the bottom of the inverter chassis.

Step 3 (Optional) Measure the temperatures at the joints between DC terminals and connectors using a point-test thermometer.

To ensure that the DC terminals are in good contact, check the temperatures at the joints between DC terminals and connectors after the SUN2000 has been running for a period of time. Ensure that the temperature rise does not exceed 40°C.

Step 4 Connect with SUN2000APP as advanced user and check the inverter status

Login as Advanced user with SUN2000APPàRunning InfoàDetailsàCheck the inverter status

 

 

Powering Off the SUN2000


After the SUN2000 powers off, the remaining electricity and heat may still cause electric shocks and body burns. Therefore, put on protective gloves and begin servicing the SUN2000 five minutes after the power-off.

Procedure

Step 1 Run a shutdown command on the SUN2000 APP

Login as Advanced user with SUN2000APPàMaintenanceàPower off

Step 2 Turn off the AC switch between the SUN2000 and the power grid.

Step 3 Set the two DC switches to OFF.

 

Huawei Enterprise Technical Assistant Center will assist you 24x7

E-mail: eu_inverter_support@huawei.com
24*7 Hotline:

Europe +80 03 38 88 888  (except below countries):

Croatia/Latvia/Bulgaria +80 07 77 78 899

Iceland 800201866 Slovakia +40 31 22 61 915 Moldova 080061466

Serbia 800190899 Lithuania 880031499 Romania 0800400897

Australia 1800046639 Canada +40 31 22 61 915 New Zealand 080061466

America 1 877 9huawei

Link: http://solar.huawei.com/


Comment

You need to log in to comment to the post Login | Register
Comment

Notice: To protect the legitimate rights and interests of you, the community, and third parties, do not release content that may bring legal risks to all parties, including but are not limited to the following:
  • Politically sensitive content
  • Content concerning pornography, gambling, and drug abuse
  • Content that may disclose or infringe upon others ' commercial secrets, intellectual properties, including trade marks, copyrights, and patents, and personal privacy
Do not share your account and password with others. All operations performed using your account will be regarded as your own actions and all consequences arising therefrom will be borne by you. For details, see " User Agreement."

My Followers

Login and enjoy all the member benefits

Login

Block
Are you sure to block this user?
Users on your blacklist cannot comment on your post,cannot mention you, cannot send you private messages.
Reminder
Please bind your phone number to obtain invitation bonus.