Power Not enough Message is reported on OSN9800U16 during the Commissioning

106 0 0 0 0

Hello everyone!

Today, I’d like to share a case.

 

Problem Description

During the Commissioning of one OSN9800U16 ,The U2000 Failed to Add  Verify the Boards in the shelf and apply the configuration ; the U2000 Sever version was U2000V2R16C60

The U2000 Prompted the message POWER NOT ENOUGH was displayed when trying to FINISH the Configuration;

1


Problem Analysis

To fix the issue we have followed the steps below:

 

1. Double check the Power requirements provided by the customer : the Circuit breakers and their capacity

below are the Standards requirements

2

 

1.1. Above table is showing the requirements but  on site the SBC used the copper fitting 2 in 1  so instead of 4*63A breakers we  had  2*63A breakers

 

1.2. After remove the  copper fitting  the Problem was still   existing but only Service Boards failed to be Added  1*U210, 1*S216, 1*T220

3

 

2.  Check if the Power requirements  have been configured through the U2000 and Match the  Hardware configuration in term of Power

 

2.1. the PIUS Distribution is as below:

PIU 1A-- connected to 1*63A Breaker is connected to the lower part of OSN subrack  to supply the EFI Boards and Cross connections boards

PIU 2A -- Connected to 1*63A Breaker is connected to the Upper Part of the OSN subrack to supply all the Services boards

PIU1B &2B are the backup of the previous one a

 

2.2.  the Rated Current set for PIU 1A and PIU2A should match the current site configuration

4

 

2.3. PIU on the slot 68A succeeded to supply the Lower part but PIU on the slot 69 did not because of Shorter copper fitting which divide the RAted current from 63A to 63A/ 2; so the the software and Hardware configuration

were not consistent and Boards failed to be addeed

3. I ve set Remove the Copper fitting 2 in 1 , provide for Each PIU 1 *63A Circuit breakers then Set 63 A for PIU 68  and 63A for PIU 69;

As a result The commissioning SUCCEEDED and The Power consumption are below

5

 

POWER CONSUMPTION:

6

 

Root Cause

WRONG CONFIGURATION Of the Power distribution from the customer rectifier to the OSN DCDB and Wrong configuration on the Power specifications on the U2000 during the commissioning stp.

 

Solution Description

1.  To Strictly Respect the Power requirement for the OSN9800U16: 4*63A Circuit breakers, using 25mm2 Power cable; Maximum distance is 30m using this cable type.

2.  To Match the Hardware configuration of the Power with the Configuration through the U2000 , CORRECTLY set the Circuit breakers  rated current.

7

 

Suggest

Double check the Power specifications of each products and submit the requirements to our customer , Follow the SBC onsite during the Power on.

 

Welcome to leave a message below.

We’ll study together.

Thank you!


Comment

You need to log in to comment to the post Login | Register
Comment

Notice: To protect the legitimate rights and interests of you, the community, and third parties, do not release content that may bring legal risks to all parties, including but are not limited to the following:
  • Politically sensitive content
  • Content concerning pornography, gambling, and drug abuse
  • Content that may disclose or infringe upon others ' commercial secrets, intellectual properties, including trade marks, copyrights, and patents, and personal privacy
Do not share your account and password with others. All operations performed using your account will be regarded as your own actions and all consequences arising therefrom will be borne by you. For details, see " User Agreement."

My Followers

Login and enjoy all the member benefits

Login

Block
Are you sure to block this user?
Users on your blacklist cannot comment on your post,cannot mention you, cannot send you private messages.
Reminder
Please bind your phone number to obtain invitation bonus.