Hi Herediano,
Follows my explanation, and I hope this helps you!!!
To a large network cutover, it is necessary divided into multiple small cutovers. In this case, a general cutover scheme and many specific cutover schemes are required to describe the whole process.
Generally, perform the following steps to write a large-scale network cutover solution:
1. Describe the project background
2. Formulate the overall cutover scheme and plan.
Many network cutover solutions cannot be completed in one step. Generally, they are divided into multiple small cutover schemes. In this case, a general cutover scheme and many specific cutover schemes are required to describe the whole process.
The cutover solution not only describes the tasks that need to be performed during the cutover but also contains the schedule of each task. Therefore, the related contents need to be discussed and approved by the cooperation departments and units.
3. Prepare specific cutover implementation tasks.
Preparations Before the cutover
Migration networking diagram
Scope and Risks of cutover and go-live
Organization and Personnel Arrangement
Formal cutover Procedure and Process
Rollback Procedure
4. After the cutover is complete, observe the on-duty observation after the cutover.
On-site on-duty: After all the cutover steps and test steps are complete, enter the observation period. Generally, if the cutover is normal within 24 hours, the cutover is successful
The migration may also fail. In this case, an emergency solution or rollback solution is required.
Good Luck!!!