After you install the eA680, perform a hardware installation check and a power-on check.
Prerequisites
The eA680-208 hardware has been installed.
Procedure
Step 1: Check whether the eA680 hardware is correctly installed.
When performing the hardware check for the eA680, check the items listed in Table 1 in order.
Table 1 Hardware installation check of the eA680
![]()
When checking the cable connections of the eA680-208, check the items listed in Table 2 in order.
Table 2 Cable connection check of the eA680
![]()
Step 2: Perform the power-on check, as shown in Figure 1.
Figure 1 Power-on check of the eA680
![]()
The items listed in Table 3 must be checked during eA680 indicator check.
Table 3 Indicator Check
![]()
NOTE:If the RSSI indicator is off when the eA680 powers on, the signal strength is too weak. Check the
power supply and the angle of the angle adjusting component.
---End
You are welcomed to visit our “Enterprise Wireless Information Center” for further document.
http://support.huawei.com/onlinetoolsweb/elte/Info_en.jsp
This post was last edited by Mr.Bright at 2019-01-11 03:29.