How to commission IEEE 1588v2 on site?

Latest reply: Dec 29, 2018 02:07:27 2257 2 7 0 0

Hello, Community!


This post explains the procedure of how to commission IEEE 1588v2 on site. Please have a read further down.


IEEE 1588v2

PROCEDURE


1. Check configurations.


2. After completing IEEE 1588v2-related configurations according to the network design diagrams, check the configurations based on parameters specified in the Clock Configuration List for xxx Office. For operation details, see section 3.4.


3. Formulate a commissioning plan.


4. Determine a proper commissioning sequence according to connections of OTN equipment to BITS devices and PTN equipment.


  • First commission BITS devices.


  • Configure delay compensation along the BITS link and ensure that the source of delay compensation ports is BITS.


  • For a ring network, disable ports to trigger clock source switching and record the switching. After delay compensation at the standby clock tracing link is completed, restore configurations.


  • For PTN equipment where IEEE 1588v2 has been provided, configure delay compensation on all OTN boards before connecting OTN equipment to PTN equipment.


5. Start commissioning on site.


Start commissioning from BITS and determine a proper commissioning sequence according to site conditions. Commissioning at a site must cover all time/clock tracing links.


6. Perform short-term performance tests on site.


  • To test short-term performance after asymmetry delay compensation is completed at a site, boards can be reset (cold) after ensuring that services will not be affected.


  • For short-term performance specifications at each site, see theIEEE 1588v2 Verification Schemes for xxx FOA Site, which provides time precision requirements at each node and test cases.


  • Pre-test IEEE 1588v2 on site.


  • After all sites are commissioned, select some sites and pre-test IEEE 1588v2 according to the test cases provided in theIEEE 1588v2 Verification Schemes for xxx FOA Site.


7. Examine the pre-test results.


Examine the pre-test results and record equipment weakness.


This would be how to commission IEEE 1588v2 on site.

I think to test short-term performance after asymmetry delay compensation is completed at a site, boards can be reset (cold) after ensuring that services will not be affected.
View more
  • x
  • convention:

The 1588v2 function need the sending fiber and the receiving fiber is about the same length, otherwise this difference must be precisely compensated before it becomes usable.
View more
  • x
  • convention:

Comment

You need to log in to comment to the post Login | Register
Comment

Notice: To protect the legitimate rights and interests of you, the community, and third parties, do not release content that may bring legal risks to all parties, including but are not limited to the following:
  • Politically sensitive content
  • Content concerning pornography, gambling, and drug abuse
  • Content that may disclose or infringe upon others ' commercial secrets, intellectual properties, including trade marks, copyrights, and patents, and personal privacy
Do not share your account and password with others. All operations performed using your account will be regarded as your own actions and all consequences arising therefrom will be borne by you. For details, see " User Agreement."

My Followers

Login and enjoy all the member benefits

Login

Block
Are you sure to block this user?
Users on your blacklist cannot comment on your post,cannot mention you, cannot send you private messages.
Reminder
Please bind your phone number to obtain invitation bonus.