Hello, everyone.
Nice to meet you again.
I wonder if you have encountered any relocation equipment in your work.
I think this must be a painful experience, but also a valuable experience, such as moving your home that need to plan how to classify items, how to pack, how to move and so on。
Recently, we have completed the physical migration of the company's data center. I want to share some of your experiences and hope to help you.
The new equipment room must be constructed first. Perform the lightning protection and grounding, power distribution, and distribution networks in the new equipment room in advance, and ensure that the new equipment room is properly decorated and cleaned and ventilated and ventilated.
The equipment and cables in the old equipment room must be counted and numbered and recorded into a table. This work is not performed once. It is necessary to review the equipment and cables for at least two batches. Because people make mistakes when doing a lot of low-level repetitive work, different people do multiple reviews, which is a protection for project participants.
Protect equipment and cables to be swapped in advance. Prepare the equipment packing case and cable packing box or packing bag, and install each item to be swapped.
The most important thing is to have complete packing, handling, and storage plans. The transportation process must be planned accurately.
First, which devices and cables are installed in boxes or bags, which must be planned and recorded, and must be refined to each line.
Then, plan the installation sequence after the equipment is removed and the new equipment room, and plan the packing place after the equipment is removed and the place for unloading the equipment in the new equipment room.
Plan the package loading plan according to the freight vehicle transportation conditions, and arrange the corresponding vehicle and command personnel according to the plan.
The swap of the old equipment room is resurrected. Therefore, the equipment should be cleaned as much as possible when the equipment is dismantled. This also saves the packing personnel's clothes, regardless of whether it is good for the equipment or the packing personnel.
The new equipment room must be fully ventilated and ventilated.
The dismantling of equipment can begin in advance.
In the whole migration process, the equipment disassembly can prolong the operation time. However, the transportation process must be as fast as possible, and the intermediate time should be reduced to reduce the transportation risks.
The installation must be completed as soon as possible. In the case of a long time, the memory of related personnel is blurred, causing the device reinstallation process to be blocked.
That's all for today. I hope it will be helpful to all of you! 
If you have any other comments or want to know more, please leave a message below to let me know.