Cable latching & Fixation
|
Cable latching & Fixation Cable latching will be done through the ladder from tower to BTS room. In case of pole site cable will be latched from pole to BTS room laying through the floor ladder. CPRI cable & RRU power will be fixed by clamp in each section of the ladder separately. The CPRI cable & RRU power cable will be latched separately .Three CPRI (if required) cables will be latched together with clamp in a row & three RRU cables (if required) will be latched together with clamp in another row during installation of RRU.
|