Method used to power on OceanStor T Series V100R005 unified storage

Method used to power on OceanStor T Series V100R005 storage systems:
SAN storage system power-on procedure is as follows: switch on all the external power supplies > press the power button on any controller > power on Ethernet or Fibre Channel switches (applicable if the Ethernet or Fibre Channel switches are deployed but not powered on) > power on application servers (applicable if the application servers are not powered on).
NAS storage system power-on procedure is as follows: switch on external power supplies > power on Ethernet switches > power on Fibre Channel switches > power on storage unit controller enclosures (SUCs) and storage unit disk enclosures (SUDs) by pressing either power button of the SUC > power on file engines by pressing the power button of file engine nodes in the cluster at an interval of one minute.